Cuba estimates the generation capacity will surpass the demand by the end the year
The solution and improvement will be gradual, based on the resources that are being imported to manufacture the spare parts required by our thermoelectric power plants and generators
Author: Wennys Diaz Ballaga | internet@granma.cu
Author: Laura Mercedes Giráldez | internet@granma.cu
Author: Milagros Pichardo Pérez | internet@granma.cu
Author: Gladys Leydis Ramos López | internet@granma.cu
august 31, 2022 11:08:48
In the Cuban electricity industry not a minute has been lost, there is no discouragement in any of the workers. Photo: Cuban News Agency (ACN in Spanish)
The National Electric System (SEN in Spanish) is expected to recover 489 megawatts (MW) currently unavailable and 531 MW through other investments, as part of the gradual recovery of the electric system, an essential strategy in view of the difficult conditions the sector is currently facing, which affect the stability of the electric service to the population and the economy.
Liván Arronte Cruz, Minister of Energy and Mines recalled on Wednesday’s Round Table that SEN continues to face complex circumstances, since the thermal power plants (CTE in Spanish) Máximo Gómez, in Mariel, and Lidio Ramón Pérez, in Felton, Holguín, suffered breakdowns that made it impossible to comply with the commitment to guarantee the generation for these summer months thus losing the minimum operating reserve in the system to cover the demand.
“As it happens with every extraordinary event, the failures have been investigated by multidisciplinary teams, integrated by the competent authorities and it has been demonstrated that there was no negligence or intentionality,” he pointed out.
In the case of the Mariel thermoelectric plant, the breakdown is in unit 7, where a fire occurred, which also damaged systems and disabled unit 6, which had been in operation just for a few months, he pointed out.
The replacement for the damaged spare parts and equipment have a delivery window of more than 26 weeks, which is why it has not yet been possible to repair this unit.
At Felton, work was carried out for 120 days, 24 hours a day. Although the fire that took place there was not of great magnitude, it affected technological systems, especially the main columns of that unit, and for that reason the repair will require practically dismantling the boiler, he said. Continue reading Cuba estimates the generation capacity will surpass the demand by the end the year